QUETTA: A Senate subcommittee on problems confronting underdeveloped areas of the country reviewed progress on uplift projects for Balochistan at a meeting on Tuesday.
The members expressed concern over the proposed design of Panjgur dam and its potential impact on local communities, agricultural land and traditional irrigation systems.
The subcommittee also reviewed implementation of the province’s reserved quota in federal government jobs. The meeting of the sub-committee, held at Parliament House in Islamabad, was presided by its chairman Senator Jan Muhammad Buledi.
Planning division holds out assurance to re-examine the design
It reviewed the pace of implementation of the Aghaz-i-Haqooq-i-Balochistan Package, ongoing development projects and recruitment against the province’s quota in federal ministries and divisions.
A major chunk of the meeting was devoted to the proposed design of the Panjgur dam, its canal system and potential impact on local communities, date palm orchards, agricultural land and existing irrigation infrastructure.
Senator Buledi wondered why the existing irrigation system and its potential vulnerability had not been properly assessed before planning the project.
“Public funds spent on development schemes should bring tangible benefits to local communities rather than create additional difficulties.”
He suggested the government consider building small dams as an alternative to large dams.
National Party MNA Pullain Baloch said development projects in Balochistan should primarily serve local communities and must not damage their livelihoods, agricultural resources or economic activities. He called for a comprehensive assessment of the impact a canal for the Panjgur dam would have on local settlements and farmland.
In their reply, planning division officials said the dam’s design would be reviewed and suggestions would be sought from the irrigation department.
Irrigation network
Briefing the committee, the project director said Panjgur previously had 118 traditional Karez, which irrigated approximately 6,000 acres of agricultural land. However, the introduction of solar-powered water extraction systems had affected the traditional irrigation network, with 72 Karez already affected.
Water flows in 34 Karez have declined by over 50 per cent over the past two years.
According to the director, Panjgur dam has been designed to irrigate approximately 25,000 acres. The proposed dam will be 33 metres high, with a 30-kilometre canal on its left side and a 9.8km canal on the right side.
To protect thousands of date palms and farmland from potential damage, the original open-canal design has been revised to incorporate a pipeline-based water supply system.
The revised design has been finalised, while a cost estimate from China is awaited to determine the pipeline system’s overall expense.
The committee also reviewed the Gish Kaur dam project and sought a report from Wapda on its potential impact on downstream agriculture connected with Kech Kaur and the possible reduction in water reaching the Mirani dam.
Senator Buledi said the Establishment Division informed the committee that complete records of appointments of candidates from Balochistan in federal institutions were not available.
The subcommittee directed the Establishment Division to submit a comparative report covering appointments, vacant positions and allocated quotas.
Federal Minister for Planning Ahsan Iqbal said since Balochistan’s uplift was closely linked to the country’s overall progress, the government had committed itself to accelerating development in the province.
Published in Dawn, November 18th, 2026