Snowy Hydro 2.0 has blown out to 12 times its original cost – but the CEO says it ‘could have been worse’

admin1 min read

New projections by the Snowy Hydro company show tunnelling work is now 65% finished, but the completion date has been pushed back to 2029

The cost of Snowy Hydro 2.0 has blown out to as much as $25bn, with a major reassessment finding the long-delayed renewable energy project will not be completed until the end of the decade.

First touted by the Turnbull government in 2017 with a price tag of $2bn, the cost of the project in the Kosciuszko national park has increased dramatically over time. In 2023 it was revised to almost $13bn, with construction due to completed by the end of 2028.

Continue reading…

The post Snowy Hydro 2.0 has blown out to 12 times its original cost – but the CEO says it ‘could have been worse’ appeared first on World news | The Guardian.